Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 2.400 | 0 | 0.000 | 0.000 |
30W1369 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: dhaneti bridge UGT km 47
Administrative Approval Detail : शासनादेश सं0 499/।।।(2)/21-03(एम0एल0ए0)/2017टी.सी. दिनांक 07/01/2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
174.46
Resanction Cost :
174.46
Tentative Cost :
174.46
Exp. Upto Last Fy : 168.71
For CFY 2024-2025
Remaining : 5.75
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 168.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
8 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
9 months 2 weeks ago
30 Sep 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 07-May-2024
Physical Peramenters