Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
30W1372 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : एन0एच0एम0/निर्माण-एच0डब्लु0सी0ध्2021-22-7340
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 6.91 Lacs
Resanction Cost : 6.91 Lacs
Exp. Upto Last Fy : 6.58 Lacs
For CFY 2024-2025
Remaining : 0.33 Lacs
Demand : 0.33 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 1 month ago
28 Mar 2022
Tentative Completion date:
10 months 2 weeks ago
30 Jun 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 05-Mar-2024
Physical Peramenters