Work Profile

वन क्षेत्राधिकारी कार्यालय भटवाड़ी का नव निर्माण कार्य


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 2011/2-34 पौड़ी

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 76.25 Lacs

Resanction Cost : 76.25 Lacs

Exp. Upto Last Fy : 44.29 Lacs

For CFY 2024-2025

Remaining : 31.96 Lacs

Demand : 31.96 Lacs

Allotment : 31.96 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 44.29 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 70 %

Up to Date : 70 %

Sanction on :
2 years 1 month ago
31 Mar 2022


Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024


Actual Completion Date:
Not Yet Reported


Rating : 70

Remark

Bottelneck: no issue


कार्य प्रगति पर है। -- as on 05-Mar-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Buildings 1 1 0 1 1 0
Currently only Bank Gaurantee information is avilable