Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 0 | 1 | 1 | 0 |
30W1379 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2012/2-34 पौड़ी
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
107.34
Resanction Cost :
107.34
Tentative Cost :
107.34
Exp. Upto Last Fy : 56.68
For CFY 2024-2025
Remaining : 50.66
Demand : 50.66
Allotment : 50.66
Exp in CFY : 0.00
Total Up to Date Exp : 56.68
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
2 years 3 months ago
31 Mar 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 05-Mar-2024
Physical Peramenters