Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.625 | 2.625 | 2.620 | 0.0049999999999999 | 0.000 | 0.000 |
30W1383 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लो0नि0 अनुभाग -2 का पत्र-।ध्70891ध्2022 एवं ई-फाईल सं0- 37632
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
94.71
Resanction Cost :
94.71
Tentative Cost :
94.71
Exp. Upto Last Fy : 62.48
For CFY 2024-2025
Remaining : 32.23
Demand : 10.00
Allotment : 1.00
Exp in CFY : 0.56
Total Up to Date Exp : 63.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
1 year 8 months ago
19 Oct 2022
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण। -- as on 03-May-2024
Physical Peramenters