Work Profile Report [30W1426]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 136/रा0यो0आ0/जि0यो0/2022-23
TS Amount (lakhs) : 4 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy :
1.93
For CFY 2024-2025
Remaining :
2.07
Demand :
0.07
Allotment :
0.07
Exp in CFY :
0.00
Total Up to Date Exp :
1.93
Construction Started
Sanction on : 1 year 11 months ago
24 Jan 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 year 5 months ago
30 Jun 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 03-Mar-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand