Work Profile Report [30W1429]

नगरपालिका परिषद् बाड़ाहाट उत्तरकाशी के रामलीला मैदान से विश्वनाथ चैक तक दोनों ओर नाली निर्माण एवं सड़क मरम्मत कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 136/रा0यो0आ0/जि0यो0/2022-23

TS Amount (lakhs) : 3 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

3.00

Resanction Cost :

3.00

Tentative Cost :

3.00

Exp. Upto Last Fy :

1.50

For CFY 2024-2025

Remaining :

1.50

Demand :

1.50

Allotment :

1.50

Exp in CFY :

0.00

Total Up to Date Exp :

1.50

Unstarted Work

Sanction on : 1 year 11 months ago

24 Jan 2023

Physical Progress:

At start of FY 2024-2025 :

5 %

Up to Date :

5 %

Tentative Completion date on : 1 year 5 months ago

30 Jun 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
1
0

Remark

view all

योजना परिवर्तित की जानी है। -- as on 25-Jan-2024

Rating : 50

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: