Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 74.2 | 74.2 | 51.000 | 23.2 | 23.200 | 0.000 |
30W1460 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2451/III(2)/23-01 (Pra. Aa.)/2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
443.44
Resanction Cost :
443.44
Tentative Cost :
443.44
Exp. Upto Last Fy : 269.45
For CFY 2024-2025
Remaining : 173.99
Demand : 76.00
Allotment : 29.50
Exp in CFY : 29.49
Total Up to Date Exp : 298.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 90 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
3 months 1 week from now
30 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
90 प्रतिशत कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 03-Jul-2024