Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 0.000 | 2.4 | 2.400 | 0.000 |
30W1467 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 37632
TS Amount (lakhs) : 209.96 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
209.96
Resanction Cost :
209.96
Tentative Cost :
209.96
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 209.86
Demand : 100.00
Allotment : 64.80
Exp in CFY : 72.34
Total Up to Date Exp : 72.44
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 60 %
Sanction on :
7 months 2 weeks ago
28 Nov 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ह्यूम पाईप, रिटेनिंग वाल एवं जी-1,जी-2 का कार्य पूर्ण तथा जी-3 का कार्य प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters