Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
30W1495 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 43/VIII-DP-07/लो0नि0वि0(01)/जि0यो0/2023-24
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy : 1.98
For CFY 2024-2025
Remaining : 1.02
Demand : 1.02
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
8 months 2 weeks ago
27 Oct 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 30-Jan-2024