Work Profile

ग्राम सभा दिखोली मे तामेश्वर मन्दिर परिसर मे जल धारा तक पैदल मार्ग पी0सीसी0 निर्माण कार्य


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : 43/VIII-DP-07/लो0नि0वि0(01)/जि0यो0/2023-24

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 3.00 Lacs

Resanction Cost : 3.00 Lacs

Exp. Upto Last Fy : 1.40 Lacs

For CFY 2024-2025

Remaining : 1.60 Lacs

Demand : 1.60 Lacs

Allotment : 0.10 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 1.40 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 60 %

Sanction on :
6 months 3 weeks ago
27 Oct 2023


Tentative Completion date:
3 months 1 week from now
31 Aug 2024


Actual Completion Date:
Not Yet Reported


Rating : 131

Remark

Bottelneck: no issue


कार्य प्रगति पर है। -- as on 30-Jan-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 0 1 1 0