Work Profile

30W1520 :

No Pic Avilable Time series Gantt
वर्ष 2024-25 मे वार्षिक अनुरक्षण के अन्तर्गत सिलक्यारा-बनगांव-चापड़ा-सरोट मोटर मार्ग के किमी0 6, 7, 8, 9, 14 एवं 15 मे बी0सी0 द्वारा नवीनीकरण का कार्य


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : ENC No. 191/14Yata(Ka)-U./2023

TS Amount (lakhs) : 0 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

131.46

Resanction Cost :

131.46

Tentative Cost :

131.46

Exp. Upto Last Fy : 0.00

For CFY 2024-2025

Remaining : 131.46

Demand : 131.46

Allotment : 126.00

Exp in CFY : 125.57

Total Up to Date Exp : 125.57

in Tendering Stage

Physical Progress:

At start of FY 2024-2025 : 10 %

Up to Date : 100 %

Sanction on :
5 months 1 week ago
09 Feb 2024


Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


कार्य पूर्ण। -- as on 09-Jul-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 6.43 6.43 0.000 6.43 6.430 0.000
Currently only Bank Gaurantee information is avilable