Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 42 | 42 | 0.000 | 42 | 42.000 | 0.000 |
30W1522 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 212/III(2)/2024-01(Pra.Aa)/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
311.75
Resanction Cost :
311.75
Tentative Cost :
311.75
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 311.75
Demand : 291.75
Allotment : 87.50
Exp in CFY : 87.08
Total Up to Date Exp : 87.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 75 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 03-Jul-2024
Physical Peramenters