Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.85 | 0.85 | 0.000 | 0.85 | 0.850 | 0.000 |
30W1529 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No. 51659
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.04
Resanction Cost :
74.04
Tentative Cost :
74.04
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 74.04
Demand : 40.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 1 %
Sanction on :
4 months 1 day ago
16 Mar 2024
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदाऐं आमंत्रित। दिनांक 11-07-2024 को निविदाऐं प्राप्त ।अनुबंध गठन की कार्यवाही की जा रही है l -- as on 13-Jul-2024
Physical Peramenters