Work Profile Report [30W1533]

जनपद मुख्यालय उत्तरकाशी के कलक्ट्रेट आवासीय कालोनी के मरम्मत कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E File No. 124590

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

350.00

Resanction Cost :

350.00

Tentative Cost :

350.00

Exp. Upto Last Fy :

0.85

For CFY 2024-2025

Remaining :

349.15

Demand :

349.15

Allotment :

99.15

Exp in CFY :

80.35

Total Up to Date Exp :

81.20

Construction Started

Sanction on : 1 year 7 months ago

25 May 2023

Physical Progress:

At start of FY 2024-2025 :

15 %

Up to Date :

15 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
0
1
1
0

Remark

view all

कार्य प्रगति पर है। -- as on 08-Apr-2024

Rating : 33

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: