Work Profile

जनपद मुख्यालय उत्तरकाशी के कलक्ट्रेट आवासीय कालोनी के मरम्मत कार्य


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : E File No. 124590

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 350.00 Lacs

Resanction Cost : 350.00 Lacs

Exp. Upto Last Fy : 0.85 Lacs

For CFY 2024-2025

Remaining : 349.15 Lacs

Demand : 349.15 Lacs

Allotment : 99.15 Lacs

Exp in CFY : 16.47 Lacs

Total Up to Date Exp : 17.32 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 15 %

Up to Date : 15 %

Sanction on :
11 months 3 weeks ago
25 May 2023


Tentative Completion date:
10 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 45

Remark

Bottelneck: no issue


कार्य प्रगति पर है। -- as on 08-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Jobs 1 1 0 1 1 0
Currently only Bank Gaurantee information is avilable