Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.14 | 2.14 | 2.140 | 0 | 0.000 | 0.000 |
30W1538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Letter No. 258/14 Pra.Yata.(Ka)-U/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.81
Resanction Cost :
35.81
Tentative Cost :
35.81
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 35.81
Demand : 35.81
Allotment : 35.81
Exp in CFY : 29.70
Total Up to Date Exp : 29.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 08-Apr-2024
Physical Peramenters