Work Profile Report [30W1539]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : DM Letter No. 1075/VIII-DP-07-JY/2023-24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
3.00
Demand :
3.00
Allotment :
1.50
Exp in CFY :
1.49
Total Up to Date Exp :
1.49
Construction Started
Sanction on : 1 year 1 week ago
12 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
30 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 15-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand