Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.21 | 3.21 | 3.21 | 0 |
30W1543 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 388/14याता0(क)-उ0/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 48.15 Lacs
Resanction Cost : 48.15 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 48.15 Lacs
Demand : 48.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 4 days ago
15 Mar 2024
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
आदर्श आचार संहिता के उपरान्त निविदा आमंत्रित की जायेगी। -- as on 30-Apr-2024
Physical Peramenters