Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 7.000 | 0.000 |
30W514 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2195 (1)/।।।(2)/13-47 (प्रा0आ0)/2012 दि0 22-03-13
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 88.20 Lacs
Resanction Cost : 88.20 Lacs
Exp. Upto Last Fy : 10.69 Lacs
For CFY 2024-2025
Remaining : 77.51 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.69 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
11 years 1 month ago
22 Mar 2013
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
fववाद सुलझा fदया गया है। सर्वेक्षण पुनः कर fलया गया हैं समरेखण स्वीकृत। इस कार्यालय के पत्रांक 752/वनभूमि, दिनांक 03.05.2024 द्वारा वनभूमि प्रस्ताव प्रतिहस्ताक्षर हेतु प्रभागीय वनाधिकारी को प्रेषित। -- as on 07-May-2024
Physical Peramenters