Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
30W639 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5126/।।।(2)/14-06 (मु0म0घो0)/2014 दि0 17-10-14
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.06
Resanction Cost :
27.06
Tentative Cost :
27.06
Exp. Upto Last Fy : 10.91
For CFY 2024-2025
Remaining : 16.15
Demand : 16.00
Allotment : 10.00
Exp in CFY : 7.67
Total Up to Date Exp : 18.58
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 9 months ago
17 Oct 2014
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
शा0सं0- 2307/।।।(2)/16-03 (एम0एल0ए0)/15 दिनांक 11-08-16 द्वारा द्वितीय चरण की रू0 284.38 लाख की स्वीकृति प्राप्त। वनभूमि की सैद्धान्तिक स्वीकृति प्राप्त।विधिवत स्वीकृत अपेक्षित। पहाड़ कटान का कार्य पूर्ण। मुआवजा वितरण की कार्यवाही प्रगति पर है। -- as on 29-Jun-2024
Physical Peramenters