Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.100 | 0.4 | 0.400 | 0.000 |
30W640 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5126/।।।(2)/14-06 (मु0म0घो0)/2014 दि0 17-10-14
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.57
Resanction Cost :
31.57
Tentative Cost :
31.57
Exp. Upto Last Fy : 11.32
For CFY 2024-2025
Remaining : 20.25
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 years 9 months ago
17 Oct 2014
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
वनभूमि प्रस्ताव संख्या-एफ0पी0/यू0के/रोड़/ 18730/2016 दिनांक 29.03.2016 के द्वारा आॅन-लाईन किया जा चुका है। विधिवत स्वीकृति प्राप्त है। द्वितीय चरण की स्वीकृति प्राप्त। 3.10 किमी0 तक कार्य पूर्ण। किमी0 3.10 के बाद ग्रामीणों का विवाद है। मुआवजा वितरण की कार्यवाही प्रगति पर। -- as on 04-May-2024
Physical Peramenters