Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
30W641 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5126/।।।(2)/14-06 (मु0म0घो0)/2014 दि0 17-10-14
TS Amount (lakhs) : 36.08 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
36.08
Resanction Cost :
36.08
Tentative Cost :
36.08
Exp. Upto Last Fy : 17.79
For CFY 2024-2025
Remaining : 18.29
Demand : 18.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 17.79
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
9 years 9 months ago
17 Oct 2014
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
द्वितीय चरण स्टेज-। की स्वीकृति प्राप्त है। कार्य पूर्ण। डिफेक्ट कटिंग का कार्य प्रगति पर। मुआवजा वितरण की कार्यवाही प्रगति पर। -- as on 03-May-2024
Physical Peramenters