Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
31W123 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शा0सं0-5384 1/(।।।) 2/10-02 एम0एल0ए0/2010 दि0- 13/12/2010
TS Amount (lakhs) : 37.8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 32.21
For CFY 2024-2025
Remaining : 5.59
Demand : 5.59
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 32.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 7 months ago
13 Dec 2010
Tentative Completion date:
7 years 4 months ago
01 Mar 2017
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। द्वितीय चरण का कार्य पूर्ण। भूमी सम्बन्धी आपसी विवाद के कारण कुछ कास्तकारो का भूमि प्रतिकर दिया जाना शेष है। -- as on 02-Mar-2024
Physical Peramenters