Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
31W125 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शा0सं0-5384 1/(।।।) 2/10-02 एम0एल0ए0/2010 दि0- 13/12/2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 12.60 Lacs
Resanction Cost : 12.60 Lacs
Exp. Upto Last Fy : 3.22 Lacs
For CFY 2024-2025
Remaining : 9.38 Lacs
Demand : 9.38 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.22 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
13 years 5 months ago
13 Dec 2010
Tentative Completion date:
5 years 1 month ago
31 Mar 2019
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण के अन्तर्गत प्रतिकर भुगतान की कार्यवाही गतिमान है। द्वितीय चरण पार्ट-1 का कार्य पूर्ण। -- as on 02-Mar-2024
Physical Peramenters