Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.57 | 0.57 | 0.570 | 0 | 0.000 | 0.000 |
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
31W33 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी के पत्रांक-477/जि0 यो0-ओ0एस0डी0/2013 दि0-23.09.2013
TS Amount (lakhs) : 17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.00
Resanction Cost :
17.00
Tentative Cost :
17.00
Exp. Upto Last Fy : 15.03
For CFY 2024-2025
Remaining : 1.97
Demand : 1.97
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 15.03
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
10 years 9 months ago
23 Sep 2013
Tentative Completion date:
9 years 9 months ago
30 Sep 2014
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Mar-2023
Physical Peramenters