Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
31W409 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : -शा0 सं0-535/।।। 2 /16-03 एम0एल0ए0/2015 दिनांक 29 फरवरी 2016
TS Amount (lakhs) : 149.75 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
149.75
Resanction Cost :
149.75
Tentative Cost :
149.75
Exp. Upto Last Fy : 95.73
For CFY 2024-2025
Remaining : 54.02
Demand : 54.02
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 95.73
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
8 years 4 months ago
29 Feb 2016
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य पूर्ण। दायित्वों का भुगतान शेष है। उक्त कार्य का वनभूमि प्रस्ताव त्रुटिवश प्रथम चरण एवं द्वितीय चनण दोनो में अंकित हो गया था, जिस कारण उक्त कार्य के द्वितीय चरण से वन भूमि प्रस्ताव Withdraw कर लिया गया है। -- as on 14-Jul-2024
Physical Peramenters