Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
31W702 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी उत्तरकाशी का पत्रांक 282/तेरह-आ0प्र0प्राधि0/न्यूनी0निधि0/2022-23 दिनांक 21/07/2022
TS Amount (lakhs) : 3.98 Lacs
Financial Detail
Sanction Cost : 3.98 Lacs
Resanction Cost : 3.98 Lacs
Exp. Upto Last Fy : 1.99 Lacs
For CFY 2024-2025
Remaining : 1.99 Lacs
Demand : 1.99 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.99 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 9 months ago
21 Jul 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 31-Mar-2023
Physical Peramenters