Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
No of Bridges | 1 | 2 | 0 | 2 | 2 | 0 |
Span of Bridges [m] | 70 | 70 | 0.000 | 70 | 70.000 | 0.000 |
31W715 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई फाईल संख्या 40949 दि0 19/12/2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.70
Resanction Cost :
25.70
Tentative Cost :
25.70
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 25.60
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 6 months ago
19 Dec 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग का सर्वेक्षण कर लिया गया है, समरेखन प्रस्ताव गठित किया जा रहा है। -- as on 14-Jul-2024
Physical Peramenters