Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
31W720 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला खनिज फाॅउन्डेशन न्यास, प्रकोष्ठ, क0 नं0 13- गंगोत्री भवन, कलेक्ट्रेट परिसर, जनपद उत्तरकाशी का पत्रांक 57/जि0खनि0फा0-उ0का0/डी0एम0एफ0/2022-23 दि0 31/12/2022
TS Amount (lakhs) : 10 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 6.00
For CFY 2024-2025
Remaining : 4.00
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 6 months ago
31 Dec 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 31-Mar-2023
Physical Peramenters