Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.000 | 0.5 | 0.500 | 0.000 |
31W737 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-ई फाईल 37632 दिनांक 16 जनवरी 2023
TS Amount (lakhs) : 56.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.21
Resanction Cost :
56.21
Tentative Cost :
56.21
Exp. Upto Last Fy : 19.29
For CFY 2024-2025
Remaining : 36.92
Demand : 36.92
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.29
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 90 %
Sanction on :
1 year 6 months ago
16 Jan 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य 90 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 14-Jul-2024
Physical Peramenters