Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.000 | 0.5 | 0.500 | 0.000 |
31W737 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-ई फाईल 37632 दिनांक 16 जनवरी 2023
TS Amount (lakhs) : 56.21 Lacs
Financial Detail
Sanction Cost : 56.21 Lacs
Resanction Cost : 56.21 Lacs
Exp. Upto Last Fy : 19.29 Lacs
For CFY 2024-2025
Remaining : 36.92 Lacs
Demand : 36.92 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.29 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
1 year 4 months ago
16 Jan 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य 65 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 02-Mar-2024
Physical Peramenters