Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
31W773 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 ई0 फाईल सं0 45771 लो0नि0वि0 अनुभाग 2 दि0 21 फरवरी 2023
TS Amount (lakhs) : 30.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.02
Resanction Cost :
30.02
Tentative Cost :
30.02
Exp. Upto Last Fy : 27.21
For CFY 2024-2025
Remaining : 2.81
Demand : 2.81
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
21 Feb 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 02-Mar-2024
Physical Peramenters