Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 1.500 | 0.5 | 0.500 | 0.000 |
31W775 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 ई0 फाईल सं0 40949 लो0नि0वि0 अनुभाग 2 दि0 01 मार्च 2023
TS Amount (lakhs) : 158.47 Lacs
Financial Detail
Sanction Cost : 158.47 Lacs
Resanction Cost : 158.47 Lacs
Exp. Upto Last Fy : 92.74 Lacs
For CFY 2024-2025
Remaining : 65.73 Lacs
Demand : 65.73 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 92.74 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 2 months ago
01 Mar 2023
Tentative Completion date:
3 months 1 week from now
27 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य 70 प्रतिशत पूर्ण। शेष कार्य प्रगति पर है। -- as on 03-Apr-2024