31W781 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0- ई फाईल सं0 49297 दि0 20 मार्च 2023।
TS Amount (lakhs) : 14.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.39
Resanction Cost :
14.39
Tentative Cost :
14.39
Exp. Upto Last Fy : 2.42
For CFY 2024-2025
Remaining : 11.97
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.42
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
1 year 3 months ago
20 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त सेतु का सर्वेक्षण करवाकर प्रथम स्टेज का डिजाईन जिसमे जियोटेकनिकल इन्वेस्टिगेशन एवं हाइड्रोलाजिकल इन्वेस्टिेगेशन सम्मिलित है को जाॅच हेतु विभागीय डिजाईन सेल को प्रेषित कर दिया गया है। -- as on 06-Feb-2024
Physical Peramenters