Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.69 | 3.69 | 0.000 | 3.69 | 3.690 | 0.000 |
31W789 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन ई पत्रावली संख्या 48456 दि0 10 अगस्त 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 70.71 Lacs
Resanction Cost : 70.71 Lacs
Exp. Upto Last Fy : 6.80 Lacs
For CFY 2024-2025
Remaining : 63.91 Lacs
Demand : 63.91 Lacs
Allotment : 26.22 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.80 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
4 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य गतिमान है। -- as on 12-Feb-2024