Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
31W796 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 37632 दि0 28/08/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
188.32
Resanction Cost :
188.32
Tentative Cost :
188.32
Exp. Upto Last Fy : 54.95
For CFY 2024-2025
Remaining : 133.37
Demand : 133.37
Allotment : 50.00
Exp in CFY : 26.96
Total Up to Date Exp : 81.91
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 80 %
Sanction on :
10 months 2 weeks ago
28 Aug 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डामरीकरण का कार्य पूर्ण। दीवारों एवं नाली निर्माण का कार्य 80 प्रतिशत पूर्ण, शेष कार्य प्रगति पर है। -- as on 02-Jul-2024
Physical Peramenters