Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
31W796 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 37632 दि0 28/08/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 188.32 Lacs
Resanction Cost : 188.32 Lacs
Exp. Upto Last Fy : 54.95 Lacs
For CFY 2024-2025
Remaining : 133.37 Lacs
Demand : 133.37 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 54.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
8 months 3 weeks ago
28 Aug 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों एवं नाली निर्माण का कार्य प्रगति पर है। डामरीकरण का कार्य प्रारम्भ किया जाना है। -- as on 02-Mar-2024
Physical Peramenters