Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 1.000 | 1 | 1.000 | 0.000 |
31W798 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल संख्या 37632 दि0 28/08/2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.02
Resanction Cost :
74.02
Tentative Cost :
74.02
Exp. Upto Last Fy : 38.05
For CFY 2024-2025
Remaining : 35.97
Demand : 35.97
Allotment : 0.00
Exp in CFY : 14.19
Total Up to Date Exp : 52.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
10 months 2 weeks ago
28 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण पार्ट-1 का कार्य 100 प्रतिशत पूर्ण। -- as on 14-Jul-2024
Physical Peramenters