Work Profile Report [31W855]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला विकास अधिकारी उत्तरकाशी का पत्रांक 1596/जि0यो0-2023-24 दि0 20 नवम्बर 2023।
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
29.00
Resanction Cost :
29.00
Tentative Cost :
29.00
Exp. Upto Last Fy :
15.43
For CFY 2024-2025
Remaining :
13.57
Demand :
13.57
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
15.43
Construction Started
Sanction on : 1 year 3 days ago
20 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
70 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 22-May-2024