Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.18 | 20.18 | 0.000 | 20.18 | 0.000 | 0.000 |
31W856 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 5347/।।। (2)/2023-01 (प्रा0आ0)/2023 दि0 05 दिसम्बर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.84
Resanction Cost :
218.10
Tentative Cost :
218.10
Exp. Upto Last Fy : 170.56
For CFY 2024-2025
Remaining : 47.54
Demand : 47.54
Allotment : 47.54
Exp in CFY : 0.00
Total Up to Date Exp : 170.56
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। उक्त कार्य के शासनादेश में कार्य को दो भागो में तोडकर, स्वीकृत लागत अलग अलग दर्शायी गयी थी, जिस कारण उक्त कार्य को दो भागो में आनलाईन एम0आई0एस0 में अंकित किया गया। परन्तु उक्त कार्य को एक कार्य के रूप में ही अंकित किया जाना था। अतः वर्तमान में इस कार्य की लागत को पुनःरीक्षित कर दिया गया है। उक्त कार्य में भटवाडी बार्सू मोटर मार्ग हेतु रोड सेफ्टी का कार्य भी सम्मिलित है। -- as on 10-Apr-2024
Physical Peramenters