Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
32W1022 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1259/।।। (2)/19-02 (एम0एल0ए0)/2017 टी.सी. ।।, दिनांक 07.03.2019
TS Amount (lakhs) : 131.11 Lacs
Financial Detail
Sanction Cost : 131.11 Lacs
Resanction Cost : 131.11 Lacs
Exp. Upto Last Fy : 129.61 Lacs
For CFY 2024-2025
Remaining : 1.50 Lacs
Demand : 1.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 129.61 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
5 years 2 months ago
07 Mar 2019
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 15-Jun-2022
Physical Peramenters