Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 1.700 | 0 | 0.000 | 0.000 |
32W1074 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नाबार्ड का पत्रांक रा.बै. उत्तर क्षेत्र का. एस.पी.डी.आर.-16 आर.आई.डी.एफ. 26 72 आई.एस.सी. 12.11.20, दिनांक 18.11.2020
TS Amount (lakhs) : 129.18 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
129.18
Resanction Cost :
137.90
Tentative Cost :
137.90
Exp. Upto Last Fy : 133.75
For CFY 2024-2025
Remaining : 4.15
Demand : 4.15
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 133.75
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 7 months ago
18 Nov 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य की मूल स्वीकृत लागत रू. 129.18 लाख है, परन्तु नाबार्ड द्वारा मार्ग के रख-रखाव कार्य के मद तीन वर्ष हेतु बढ़ाये जाने के फलस्वरूप पुनरीक्षित स्वीकृति रू. 137.90 लाख की प्रदान की गयी है। निर्माण कार्य पूर्ण। अन्य विविध कार्य प्रगति पर। -- as on 03-Sep-2021
Physical Peramenters