Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.22 | 3.22 | 3.220 | 0 | 0.000 | 0.000 |
32W1075 :
Work not linked with IM
Bridges on The Basis of AI: STEEL GIRDER BRIDGE DICHLI
Administrative Approval Detail : नाबार्ड का पत्रांक रा.बै. उत्तर क्षेत्र का. एस.पी.डी.आर.-16 आर.आई.डी.एफ. 26 72 आई.एस.सी. 12.11.20, दिनांक 18.11.2020
TS Amount (lakhs) : 245.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
262.49
Resanction Cost :
262.49
Tentative Cost :
262.49
Exp. Upto Last Fy : 249.89
For CFY 2024-2025
Remaining : 12.60
Demand : 12.60
Allotment : 5.50
Exp in CFY : 6.52
Total Up to Date Exp : 256.41
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
3 years 7 months ago
18 Nov 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त कार्य नाबार्ड का पत्रांक रा.बै. उत्तर क्षेत्र का. एस.पी.डी.आर.-16 आर.आईडी.एफ. 26 72 आई.एस.सी. 12.11.20, दिनांक 18.11.2020 के द्वारा नाबार्ड-26 में स्वीकृत होने के फलस्वरूप प्रगति नाबार्ड-26 में दर्शायी जा रही है। कार्य में नाबार्ड द्वारा मेन्टेनेन्स सहित पुनरीक्षित लागत स्वीकृत की गयी है। -- as on 13-Sep-2023
Physical Peramenters