Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
32W1099 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 311/रा.यो.आ./जि.यो/2021-22., दिनांक 26.07.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy : 4.98
For CFY 2024-2025
Remaining : 0.02
Demand : 0.02
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 11 months ago
26 Jul 2021
Tentative Completion date:
3 months 3 weeks ago
25 Mar 2024
Actual Completion Date:
3 months 3 weeks ago
25 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 15-Jun-2022
Physical Peramenters