Work Profile Report [32W1100]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 311ध्रा.यो.आ.ध्जि.योध्2021-22., दिनांक 26.07.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
15.00
Tentative Cost :
15.00
Exp. Upto Last Fy :
10.97
For CFY 2024-2025
Remaining :
4.03
Demand :
4.03
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
10.97
Work completed
Sanction on : 3 years 3 months ago
26 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
95 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 24-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: