Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
32W1137 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 169/रा.यो.आ./जि.यो/2021-22., दिनांक 01.11.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 8.00 Lacs
Resanction Cost : 8.00 Lacs
Exp. Upto Last Fy : 2.95 Lacs
For CFY 2024-2025
Remaining : 5.05 Lacs
Demand : 5.05 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
2 years 6 months ago
01 Nov 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 15-Jun-2022
Physical Peramenters