Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
32W1152 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 312/रा.यो.आ./जि.यो/2021-22., दिनांक 26.07.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 4.00 Lacs
Resanction Cost : 4.00 Lacs
Exp. Upto Last Fy : 3.76 Lacs
For CFY 2024-2025
Remaining : 0.24 Lacs
Demand : 0.24 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.76 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
2 years 9 months ago
26 Jul 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 19-Apr-2023