Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
32W1171 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 139/रा.यो.आ./जि.यो/2022-23, दिनांक 24.01.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 8.00 Lacs
Resanction Cost : 8.00 Lacs
Exp. Upto Last Fy : 7.98 Lacs
For CFY 2024-2025
Remaining : 0.02 Lacs
Demand : 0.02 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
1 year 3 months ago
24 Jan 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 weeks ago
01 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 01-Jul-2023