Work Profile Report [32W1189]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 139/रा.यो.आ./जि.यो/2022-23
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy :
2.89
For CFY 2024-2025
Remaining :
0.11
Demand :
0.11
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.89
Work completed
Sanction on : 1 year 11 months ago
24 Jan 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 23-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: