Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 1 |
32W1193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 139/रा.यो.आ./जि.यो/2022-23
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.00
Resanction Cost :
2.00
Tentative Cost :
2.00
Exp. Upto Last Fy : 1.95
For CFY 2024-2025
Remaining : 0.05
Demand : 0.05
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 5 months ago
24 Jan 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 24-Apr-2024
Physical Peramenters