Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 1 |
32W1241 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी, उत्तरकाशी का पत्रांक 4961/तेरह-16 (2022-23), दिनांक 31.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
9.70
Resanction Cost :
9.70
Tentative Cost :
9.70
Exp. Upto Last Fy : 6.79
For CFY 2024-2025
Remaining : 2.91
Demand : 2.91
Allotment : 2.91
Exp in CFY : 2.84
Total Up to Date Exp : 9.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 13-Sep-2023
Physical Peramenters