Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.52 | 18.52 | 0.000 | 18.52 | 0.000 | 0.000 |
32W1246 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लोक निर्माण विभाग उत्तराखण्ड, देहरादून का पत्रांक 895/07 याता.-पी.एम.जी.एस.वाई.-नि. ।।।
TS Amount (lakhs) : 91.46 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.46
Resanction Cost :
91.46
Tentative Cost :
91.46
Exp. Upto Last Fy : 87.83
For CFY 2024-2025
Remaining : 3.63
Demand : 3.63
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 87.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 15-Jun-2024
Physical Peramenters